Skip to main content

Investment projects with scope: Parkland / Highridge

Total budget KSh11,550,000

Cancer diagnostic centre at Parklands Sub-County offices

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

The project has a committed budget of KES 40.0 million and is listed as fully completed. However, no payment or disbursement has been recorded.

 

Budget: KES 40.0M committed / no payment recorded.

Status: Listed as Complete – 100%, but no disbursement is documented

Construction of Machagucha Road

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

The project is marked as finished, although its actual completion rate is only 95%. No budget amount is stated, and no payment has been recorded.

 

Budget: not stated / no payment recorded.

Status: Marked finished, but actually at 95%

(mistakenly listed under Parklands/Highridge; actually belongs to Kangemi Ward)

Pedestrian footbridge at Deep Sea

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

The project had a total budget of KES 16.7 million. The full amount has been committed and paid. The project is now complete, with 100% implementation confirmed and all records reviewed and verified.

Budget: KES 16.7M committed / KES 16.7M paid.

Status: Complete – 100% (clean, verified)

Electricity connection for Parklands/Highridge Hospital

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

A total budget of KES 10.5 million was committed to the project. Although the project is listed as 100% complete, no payment or disbursement has been recorded.

Budget: KES 10.5M committed / no payment recorded.

Status: Listed as Complete – 100%, but no disbursement is documented

Rehabilitation of Matundu Lane and Matundu Close

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

A total budget of KES 22.9 million was committed, of which KES 22.8 million has been paid. Although the project is marked as finished, its actual completion rate is only 95%, indicating an inconsistency in the reported status.

 

Budget: KES 22.9M committed / KES 22.8M paid.

Status: Marked finished, but actually at 95% ("says finished, isn't")

Construction of Westlands Sub-County Office

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

A budget of KES 8.6 million has been committed to the project, but no payments have been made to date. The project is currently ongoing, with 40% of the work completed.

 

Budget: KES 8.6M committed / KES 0.0M paid.

Status: Ongoing – 40%

Rehabilitation of Githuri Road (re-tendered)

2026-08-18  •  No comments  •  Simon CDF  •  Parkland / Highridge

The full committed budget of KES 16.8 million has been disbursed. The project is listed as 100% complete, and the financial information has been verified with no discrepancies identified.

Budget: KES 16.8M committed / KES 16.8M paid.

Status: Complete – 100% (clean, verified)